Projects
- Four- Inch Mill & Pave
- Water Main Improvements
- Barrier-Free Improvements
- Two-Inch Mill & Pave
- East McClellan Avenue
- Memorial Park Master Plan
Under this contract, the Contractor will install minor drainage improvements to reduce standing water and icing within the Township right of way, replace damaged curbing, retrofit existing inlets with bicycle-safe grates and Type N curb pieces, construct barrier-free ramps, and mill and pave the following roads:
- Burlington Road
- Camelot Drive
- Collins Terrace
- Collinwood Avenue
- Crescent Road
- Keystone Drive
- Mount Pleasant Parkway
Update: Construction is complete on all of the mentioned roads.
Under this contract, Reivax will install replacement water mains and service connections on the following roads
- Bear Brook Lane
- Belvedere Drive
- East Drive
- Marberne Terrace
- North Baums Court
- Timber Hill Drive
- West Lawn Road
Update: Reivax continues construction on Bear Brook Lane and West Lawn Road.
Under this contract, Tec-Con will construct a barrier free ramp with railings at Monmouth Court to allow access between the front and rear yard recreation areas and construct four barrier free parking spaces with accessible ramps, sidewalk, and signage to allow access to Haines Pool. This project will be funded in part by a $42,265 Community Development Block Grant (CDBG) awarded to the Township in 2014.
Update: Construction is now completed.
Under this contract S. Brothers will replace damaged curbing, retrofit existing inlets with bicycle safe grates and Type N curb pieces, construct barrier free ramps and mill and pave the following roads:
- Arbor Court
- Bear Brook Court
- Highview Drive
- North Westgate Road
- Oakwood Avenue
- Sidehill Court
- Torrance Drive
Update: Paving is now completed on the mentioned roads.
Under this contract S. Brothers will replace damaged curbing, retrofit existing inlets with bicycle safe grates and Type N curb pieces, construct barrier free ramps and mill and pave East McClellan Avenue from Redwood Road to Laurel Avenue.
Update: Construction is now complete.
The Township is exploring potential improvements to Memorial Park. Have your opinion heard! What do you like about Memorial Park? What are improvements that you’d like to see - Permanent restroom facilities? Playgrounds? Fitness trails? Gardens? Benches? Let us know.
Update: Work on the Master Plan is underway by Arterial.